Tag Archives: Poliment-Redut

Admiral Nakhimov Slipping

Capture

Admiral Nakhimov at Sevmash

It’s been so widely reported it doesn’t bear much. But the sinking of SRZ-82’s PD-50 at Roslyakovo when Admiral Kuznetsov floated out seems incredible. Though it’s entirely believable given the problems afflicting Russia’s naval shipbuilding sector. In fact, it’s emblematic.

PD-50 in better days

PD-50 in better days

This has to be the “final straw” sending OSK chief Rakhmanov into retirement. Not that a new boss will be sufficient to turn this situation around.

But on to Admiral Nakhimov . . . the slipping has begun.

The TASS story from August 22 was effectively ignored in English media. That day the news agency reported the Russian Navy will not receive its renovated CGN Admiral Nakhimov until 2022.

TASS quoted Sevmash General Director Mikhail Budnichenko:

“According to the contract with OSK, the heavy nuclear-powered missile cruiser Admiral Nakhimov must be delivered to the fleet in 2022, but there are some questions with financing. I hope, and am even sure, that they will be resolved soon.”

He is more sanguine than most perhaps.

Let’s start at the beginning.

In 1988, Admiral Nakhimov was commissioned into the Soviet Navy — the third of four Kirov-class nuclear-powered guided missile cruisers. The Russian Navy sent it to the Sevmash dock for repairs in 1999 where it languished for 14 years.

Finally, in mid-2013, the MOD gave Sevmash a contract for Nakhimov’s repair and modernization. It was supposed to return to the fleet in 2018. But work on the ship didn’t commence until October 2014. About this time it was expected to rejoin the navy by 2020.

Last year, Sevmash was saying not later than 2021. Early this year, it said 2021-2022.

In August, OSK chief Rakhmanov said customer changes to the plan for Nakhimov’s modernization will take longer to complete.

Now at fully four years into its reconstruction, Admiral Nakhimov has a ways to go. In 2017, spaces were cleared for new missile (Kalibr, Tsirkon) and air defense (Poliment-Redut) systems. But no installation work had begun. Integrating these weapons into new C2 systems won’t be easy although Nakhimov may benefit some from the sore experience of outfitting proyekt 22350 frigate Admiral Gorshkov.

The repair and modernization of Petr Velikiy will obviously be put off until Nakhimov is done. Interestingly, Sevmash’s Budnichenko said the former will be renovated either at Sevmash-affiliate Zvezdochka or Baltic Shipyard, but not Sevmash itself.

All the foregoing is mainly about keeping stock. The return of Nakhimov in 2018 has now become 2022. We’ll see how it actually ends up.

Advertisements

Difficult Course to a Grand Fleet

Konstantin Bogdanov sees reason for pessimism when looking at the course ahead for rebuilding Russia’s fleet.  Writing in Friday’s Nezavisimoye voyennoye obozreniye, he says, despite an intention to spend 4.7 trillion rubles of the ten-year GPV on the Navy, there are technical challenges, clearly impractical schemes, and failures in what he calls the “organization-financial plan” ahead. 

Bogdanov provides us a handy review of the state of Russian shipbuilding.

He points first to OSK’s insistence on seeing new aircraft carriers (with nuclear-powered destroyers in their battle groups) on the Russian Navy’s horizon.  But Defense Minister Serdyukov has only a cold rebuff for the idea.  Early R&D into what a new carrier might look like is as far as he’s being willing to go.  It was made pretty clear that a carrier isn’t part of this GPV.

Bogdanov says OSK may be looking for work for the New-Admiralty Wharves it sees on Kotlin Island in the future.  The 30- to 60-billion-ruble shipyard could be ready in 2016.  An aircraft carrier project would help launch this idea.

Then Bogdanov turns to the Navy’s more immediate needs — frigates and corvettes.  

Proyekt 22350 frigates are needed by tens, if not 30, or even 40, of them.  But Northern Wharf is having trouble building them.  Lead unit Admiral of the Fleet of the Soviet Union Gorshkov was five years in construction, and its underway testing isn’t complete.  Fleet Admiral Kasatonov was laid down just about two years ago.  Its SAM system, Poliment-Redut with 9M96 missiles isn’t ready, and will have to be fitted right to finished frigates.  But Bogdanov sees the frigates’ VLS — the Multipurpose Ship Fire System (UKSK or УКСК) as a positive step.  It could fire antiship, antisubmarine, land-attack cruise missiles, torpedoes, and possibly SAMs.

When proyekt 22350 didn’t come along quickly, Bogdanov says, the Navy went for its own proyekt 11356M frigates like those being built for India.  But, he notes, Baltic Shipbuilding Plant “Yantar” in Kaliningrad isn’t having an easy time constructing them for its Indian and Russian customers.  There are delays in the Indian units, but Admiral Grigorovich and Admiral Essen have been laid down for Russia, and Admiral Makarov should join them soon.  The contract for a second batch of three was just signed.  They’re supposed to be “localized,” but may actually be more like the Indian versions.  They’re slightly cheaper than the proyekt 22350 at 10 billion vs. 16 billion rubles per ship.

Northern Wharf has the order for nine proyekt 20380 Steregushchiy-class corvettes (with the proyekt 22350 frigates this comes to more than 220 billion rubles).  Soobrazitelnyy (proyekt 20381) began sea trials this year, Boykiy was launched, Stoykiy is under construction, and Provornyy (proyekt 20385) was laid down.  Sovershennyy (proyekt 20380) remains under construction at Komsomolsk-na-Amure.  Bogdanov says the proyekt 20385 ships will have an eight-cell UKSK.

Bogdanov notes, however, that Northern Wharf’s production won’t be steady until its ownership issue is finally resolved.  If OSK takes over, this could have a good or bad effect on fulfilling defense orders, but the current financial questions around Northern Wharf are even worse.

Turning to submarines, Bogdanov believes the situation is more transparent, but there are still questions.

The SSBN picture is pretty clear.  Proyekt 955 Borey-class SSBNs finally have a missile that looks like it works.  Yuriy Dolgorukiy has fired it, and Aleksandr Nevskiy might this year.  Vladimir Monomakh is under construction, and they’re preparing production materials for Saint Nikolay.

The problem, he notes, is units 1 and 2 used sections and components of proyekt 971 and 949A submarines never built.  Units 3 and 4 will be built from scratch, and it’s too early to say how this will be reflected in their cost.  Bogdanov concludes another battle over inflated prices awaits, and there is, of course, still no 2011 contract with Sevmash.

It’s less clear with the multipurpose proyekt 885, Yasen-class, of which the Navy wants ten by 2020.  But these boats have been the focus of the Defense Ministry’s familiar complaint about unjustified price increases.  Unit 1 Severodvinsk was built from materials and resources on hand, and its rising price was frozen at 47 billion rubles in 2005.  The Defense Ministry says Sevmash wants 112 billion for unit 2 Kazan

Bogdanov thinks it’s hard to tell who’s justified here.  There is structural industrial inflation, and a higher costs could be the result of the frozen handover price on Severodvinsk.

Bogdanov mentions the thought given to cheaper attack boats like the Victor III or Akula, or proyekt 957 Kedr which never left the design phase.  The Yasen is intended to replace Soviet-era SSNs and SSGNs, but Bogdanov thinks it’s too complex and expensive to be built in the numbers Russia may need.  Twenty years ago the Russian Navy was planning for not less than 30 [sized of course against the U.S. fleet], and currently it has not more than 30 SSNs and SSGNs, and this is considered insufficient. 

Despite the uncertainty above, Bogdanov says one still hears talk about the need to develop a fifth generation submarine, but it’s unknown if there will be any development work on one.